register number |
D.0.00 Cable-operated excavator, diesel-hydraulic drive |
data processing short term |
SEILB D HYD R |
standard equipment |
D.0.00-D.0.02:
the max payload moment serves aas technical parameter.
For evaluation of the max. payload moment the max bearing capacity at 5,0 m throat at crane operation with basic jib, max counter weight, broadest track, min. 75 % of the tip-load and 360° pivoting range is taken
D.0.00- D.0.01: the stated motor/engine rating (diesel-) (kW) acc to ISO 9249 relates to the output requirements or the installed tractive force of winch (kN) without additional output requirements for attached devices. Up to 20% higher or lower installed tractive forces of winches and motor/engine ratings are considered as additional installations in the form of value increase or decrease. D.0.00-D.0.02:
The technical parameter is given by the max. nominal load moment (tm).
The max. nominal load moment is determined on the basis of the max. lifting capacity at a cantilever of 5.0 m, crane operation with basic boom, max. counterweight, widest track, at least 75 % of the moment of tilt and 360° slewing range.
D.0.00- D.0.01:
The stated (diesel) engine power (kW) as per ISO 9249 corresponds to the power required for the installed winch pulling force (kN) without additional power for attachments. Up to 20% higher or lower installed winch forces and engine powers are taken into consideration as additional equipment in the form of value increases or reductions.
Basic machine complete, designed for excavator use.
With: basic rope equipment for basic boom, counterweight (basic ballast) undercarriage track enlargement, tractor running gear, 3-grouser track pads.
Without: boom, buckets, hook block, additional equipment for supplementary hydraulic functions.
|
register of construction equipment 1991 |
3110 |
wearing part |
lifting and digging rope, rope detachment bracket, rope rollers jib head, tires
,
lifting rope and digging rope
|
characteristic |
max nominal load moment (tm) |
|
years of usage |
* |
months of rate action |
* |
monthly ratio for depreciation and interest rate |
* |
monthly ratio for costs of repair |
* |
|